Project: 1) Ore Prep Plants 2) Stacker Conveyors
Project Date: Nov ’02 – Jul ‘03
Engineering Firm:
Prime Contractor: Aqua Industrial Ltd.
Description of Work: Upgraded building Structural packages. 5 separate shutdowns of 10 days each to replace all structural support frames. Five 26,000 lbs pulleys rigged and replaced. 56,000 lbs of structural steel reworked or replaced. Engineered lift studies provided. Provided execution plans, work plans, Hazard assessments, ITP reports. Coordinated all subcontractors. 24hr continuous work shifts, completed 3 days ahead of schedule.
Click to view pictures
Atco Power
Canadian Natural Resources
Luscar Coal Valley
Opti/Nexen - Work in Progress
Opti/Nexen Longlake
Pembina
Petro Canada - Power House
Suncor Energy Inc - Access & Egress
Suncor Energy Inc - Breaker Isolation
Suncor Energy Inc - Plant 4
Suncor Energy Inc - Plant 4 upgrade
Suncor Energy Inc - Plant 16
Suncor Energy Inc - Plant 85 upgrade
Suncor Energy Inc - Scavenger Banks
Suncor Energy Inc - Steepbank Bridge
Suncor - Steepbank New Technologies
Suncor - Steepbank Reclaim Feeder
Suncor Energy Inc - Tailings Ponds
Synenco Energy Inc - Pilot Project
Trans Canada