Project: Waste Water Treatment Plant/Air Separation Unit Gasification Process
Date: September 2005— February 2008 on going
Engineering Firms: Colt Engineering/Saia Deslaurier Skadanoff
Prime Contractor: OPTI/NEXEN/ Air Liquide Canada
Sub Contractor: Aqua Industrial Ltd.
Description of Work:
Complete the structural steel erection (400 plus tons), in the main building, Lift and Rigging Vessels, tanks, skids, Steel Piping Modular's 30 total, 600 ton cold box tower at 238 feet (highest structure at Long Lake), Fin fan Units 18 total at 17tons each. Pre-commissioning assistance. Manpower increased to 200 employees in all trades in October 1st 2007. Aqua continues to work two shifts– Days and Nights into start up and commissioning.
Click to view pictures
Atco Power
Canadian Natural Resources
Luscar Coal Valley
Opti/Nexen Longlake
Pembina
Petro Canada - Power House
Suncor Energy Inc - Access & Egress
Suncor Energy Inc - Breaker Isolation
Suncor Energy Inc - Plant 4
Suncor Energy Inc - Plant 4 upgrade
Suncor Energy Inc - Plant 16
Suncor Energy Inc - Plant 85 upgrade
Suncor Energy Inc - Scavenger Banks
Suncor Energy Inc - Steepbank
Suncor Energy Inc - Steepbank Bridge
Suncor - Steepbank New Technologies
Suncor - Steepbank Reclaim Feeder
Suncor Energy Inc - Tailings Ponds
Synenco Energy Inc - Pilot Project
Trans Canada